Tuesday, October 15, 2013
Flooring
The hardwood flooring is being installed. The client chose a great product, and it looks beautiful against the interior color scheme.
Thursday, September 5, 2013
Tile Roof
After some delays receiving a competitive quote on the installation of the tile roof, we are happy to say that the crew started work on Sept 4th.
Friday, August 30, 2013
Inspections
All inspections have now been completed, and the drywall has now been loaded into the house. There are some leaks in the roof penetrations which is causing some delay, so boarding should start the first week of September.
Friday, August 23, 2013
Roofing
We lost 1 whole week searching for more competitive quotes for the tile roofing. The quotes ranged from $22k to $43k. While waiting, the waterproofing was completed on the roof, so we're ready to roll once satisfied with a price on the tile roof installation.
Friday, August 16, 2013
Soffit and Stucco
The soffit installation has been completed. Paper and wire have been set, and the scratch coat has been finished.
Tuesday, August 6, 2013
Plumbing and Heating
Plumbing and heating are now well on their way to be complete! Heating at 75%, and plumbing at 90%.
Sunday, August 4, 2013
Monday, July 15, 2013
Fast Track Construction
Construction was started on July 2. Hardly any time to update this blogsite, the roof was on the house July 11th!! We plan on pouring the concrete patio and garage on July 16th. Windows are expected to arrive on July 24th.
Tuesday, July 2, 2013
Floor Joists
Wow what a hot one today! the lumber and floor joists arrived on schedule and the boys were busy getting the crawl space insulated and the floor joists installed. The heat in the concrete crawl space was unbearable by 2:00 PM and the temperature in Ryan's truck was reading 41 Celsius. For the health and safety of the crew we shut down at 2:30 PM
Saturday, June 29, 2013
Walls and crawl space skim coat
Walls were set on Thursday June 27th and poured poured Friday June 28. Picked up an extra day or so due to pouring the skim coat at the same time as the walls. Water, power, sewer pipes were placed under the footings prior to the wall pour. The radon gas pipe and radon gravel from Bearishoff was placed Friday morning and the slab was sealed with 6 ml poly, acoustic seal caulking and tuck tape. Once the walls were poured, the final truck delivered the extra cement for the floors. On the holiday Monday July 1st the boys will be hard at work stripping the forms and prepare the top plates for the floor joists and sub floor for Tuesday.
Footings
The footings and rebar were set on Monday June 24, poured Tuesday June 25 Stripped Wednesday June 26
Excavation
Excavation was started on June Thursday June 20 with the Hitachi 200 excavator. I was fooled by the lay of the land and the proposed location of the home, thinking it was more like a 4-6 foot change in elevation. The actual change in elevation resulted in bringing up the rear footings of the house by 7 ft and dropping the entire front area of the property by over 4ft. Hauled nearly 50 truck loads of gravel packed with a 66" ride on vibrating packer, super solid foundation.