Friday, August 30, 2013
Inspections
All inspections have now been completed, and the drywall has now been loaded into the house. There are some leaks in the roof penetrations which is causing some delay, so boarding should start the first week of September.
Friday, August 23, 2013
Roofing
We lost 1 whole week searching for more competitive quotes for the tile roofing. The quotes ranged from $22k to $43k. While waiting, the waterproofing was completed on the roof, so we're ready to roll once satisfied with a price on the tile roof installation.
Friday, August 16, 2013
Soffit and Stucco
The soffit installation has been completed. Paper and wire have been set, and the scratch coat has been finished.
Tuesday, August 6, 2013
Plumbing and Heating
Plumbing and heating are now well on their way to be complete! Heating at 75%, and plumbing at 90%.
Sunday, August 4, 2013
Subscribe to: