Monday, July 15, 2013

Concrete Forming

Prepping garage pad, patio, and stair landings. Ready to pour 8 am Tuesday.

Fast Track Construction

Construction was started on July 2. Hardly any time to update this blogsite, the roof was on the house July 11th!! We plan on pouring the concrete patio and garage on July 16th. Windows are expected to arrive on July 24th.

Tuesday, July 2, 2013

Floor Joists

Wow what a hot one today! the lumber and floor joists arrived on schedule and the boys were busy getting the crawl space insulated and the floor joists installed.  The heat in the concrete crawl space was unbearable by 2:00 PM and the temperature in Ryan's truck was reading 41 Celsius.  For the health and safety of the crew we shut down at 2:30 PM